Actual data of Company A’s Cost Department for month of June’07:
Number of units produced
|
180
|
Overhead costs
|
$19,400
|
Hours worked
|
4,050
|
Number of working days
|
20
|
Company A’s Budget & Standard Costing figures
Standard hours per unit
|
20
|
Standard overhead rate per hour
|
$6.25
|
Standard fixed overhead rate per hour
|
$4.00
|
Budgeted hours per month
|
4,000
|
Budgeted working days per month
|
20
|
Question:
Compute the:
(a) “Overhead” variance
(b) Fixed production overhead volume variance
(c) Capacity variance
(d) Productivity variance
|
(a)Overhead variance:
=(SHP x OAR) less Actual cost
=[(180units x 20 hours) x $6.25]-$19,400
=(3,600 hours x $6.25)-$19,400
=$22,500-$19,400
=$3,100(F)
|
|
(b) Fixed production overhead volume variance:
=(Budgeted standard hour less SHP) x Fixed OAR
=(4,000-3,600) x $4.00
=400 x $4.00
=$1,600(A)
|
|
© Capacity variance:
=(Hours worked less Budgeted standard hours) x Fixed OAR
= (4,050-4,000) x$4.00
=50 x $4.00
=$200(F)
|
|
(e)Fixed cost productivity variance:
=(Hours worked less SHP) x $4.00
=(4,050-3,600) x $4.00
=450 x $4.00
=$1,800(A)
|
|